Dear YMCA Members and Participants,
I’m pleased to announce that we are now beginning construction on the second phase of our three phased capital development plan.
Our first phase of construction included renovations to the swimming pool and locker rooms along with a new poolside family picnic area. This upcoming second phase of construction adds a new full-size multi-purpose gymnasium, additional program space, improved landscaping, and increased parking.
Programs in our new gymnasium will include basketball, volleyball, group exercise classes, and other activities. Students at Correia Middle School will have access to our gymnasium during designated school hours for PE classes. Also, half of our gymnasium will be used temporarily to expand and relocate our fitness center (including new fitness equipment) as we prepare and execute our third and final phase of construction.
As with any project of this size, the process may result in temporary electrical, water, parking, and area closures. By staggering construction and regularly updating you, we’ll make every effort to limit disruptions and inconvenience.
Effective today, our YMCA lobby and website will include weekly updates to keep you informed of construction updates.
Please know that 100% of the funds used for construction are raised independently of your membership dues. In addition, our Annual Support Campaign funds raised in February are strictly designated for youth, families, and others in critical need of the many programs and services we continue to subsidize.
We truly value your goodwill and patronage, and appreciate your understanding throughout our construction process.
Sincerely,
Rob Sauvajot Carol Wanke Executive Director Board Chair
Haas Family Gymnasium
Phase II
Rendering

New Facility Features of Phase II:
- A new multi-use gymnasium for basketball, volleyball, group exercise classes, youth programs, gymnastics, school PE, and special events.
- New restrooms serving the family picnic area, swimming pool and gym.
- Expanded grass area for additional programming and leisure.
- Increased parking located at Correia Middle School.
- Enhanced facility landscaping.
- Pedestrian ramp in front of YMCA.
Naming Opportunities Still Remain for the "New Century" Capital Campaign.
Donate Today!
Contact Rob Sauvajot, Executive Director for more informationPhase II Estimated Construction Timeline:
May
Grading and Preparation of the Slab for the Gymnasium.
June
Relocation of Electrical Box in Front of YMCA. Continued Preparation of the Slab for the Gymnasium.
July
Erection of the Gymnasium
Building Frame. Construction of New Poolside Restrooms. Improvements to Correia Parking Lot and Landscaping. New ADA
Ramps Developed for Access to Gymnasium.
August
Complete Walls of Gymnasium and Interior Finishes. Install Wood Floor and Basketball Systems.
September
Expanded Grass Turf in Front of the Gymnasium. Construction of Pathway from Entry Breezeway to Gymnasium. Installation of New Glass Wall on Pool Deck.
October
Final Finishes and Walk Through.
November
Grand Opening of Gymnasium, Restrooms, and Surrounding Areas.
![]() | ![]() | |
![]() | ![]() | |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() |